Question
1 Approved Answer
1) Review the graph showing the contractor's estimate at completion (EAC) for the armament Work Breakdown Structure (WBS) element, along with the Governments optimistic (best
1) Review the graph showing the contractor's estimate at completion (EAC) for the armament Work Breakdown Structure (WBS) element, along with the Governments optimistic (best case) and pessimistic (worst case) EACs. Based on the graph, does the contractor's EAC appear to be reasonable?
(IMAGE DESCRIPTION: EAC chart, with dollars in the millions. Pessimistic EAC is $7.5M, Optimistic EAC is $5.7M, and Contractor's EAC is $5.0M.)
A.) It is not possible to tell from the graph where the contractors EAC falls.
B.) No, the contractors EAC is above the pessimistic EAC calculated by the Government.
C.) Yes, the contractors EAC is below the optimistic EAC calculated by the Government.
D.) No, the contractors EAC is below the range of EACs calculated by the Government.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started