1. Scott Tools produces a variety of scissors and other cutting instruments at its Statesboro manufacturing plant....
Question:
1. Scott Tools produces a variety of scissors and other cutting instruments at its Statesboro manufacturing plant. The plant is highly automated and uses an activity-based costing system to allocate overhead costs to its various product lines. The company expects to produce 30,000 total units during the current period. The costs and cost drivers associated with four activity cost pools are given below:
ACTIVITIES: | UNIT | BATCH | PRODUCT | FACILITY |
LEVEL | LEVEL | LEVEL | LEVEL | |
Cost | $70,000 | ? | $23,000 | $240,000 |
Cost Driver | 5,000 labor hrs | 120 set ups | % of use | 30,000 units |
Production of 2,000 units of a pipe-cutting tool required 600 labor hours, 16 setups, and consumed 35 % of the product sustaining activities and resulted in an overhead allocation of $34,850. What amount of batch-level overhead costs was expected during the period? (Do not round intermediate calculations.)
$2,400$18,000$32,450None of these answers is correct.
2.
Great Products Company currently outsources a relay switch that is a component in one of its products. The switches cost $23 each. The company is considering making the switches internally at the following projected annual production costs:
Unit-level material cost | $4 |
Unit-level labor cost | $3 |
Unit-level overhead | $2 |
Batch-level set-up cost (9,000 units per batch) | $46,000 |
Product-level supervisory salaries | $48,000 |
Allocated facility-level costs | $41,000 |
The company expects an annual need for 9,000 switches. If the company makes the product, it will have to utilize factory space currently being leased to another company for $3,600 a month. If the company decides to make the parts, total costs will be:
$36,800 less than if the switches are purchased. $41,000 less than if the switches are purchased. $52,200 more than if the switches are purchased. $11,200 more than if the switches are purchased.