Question
1. The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Costs Budgeted Costs Units produced 1,500 1,500 Direct
1.
The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows:
Actual Costs | Budgeted Costs | ||
Units produced | 1,500 | 1,500 | |
Direct materials cost | $5,680 | $5,010 | |
Direct labor cost | 1,620 | 1,420 | |
VOH: | |||
Maintenance | 710 | 625 | |
Power | 300 | 190 | |
FOH: | |||
Grounds keeping | 1,480 | 1,220 | |
Depreciation | 540 | 540 |
Calculate the flexible budget variance.
a.$110F
b.$1,065U
2.
c.$1,325U
d.$260F
Which of the following is true of an after-the-fact flexible budget?
a.It is a budget created in advance that is based on a particular level of activity.
b.It is used to compute what the costs should be for the level of output that actually occurred.
c.It allows managers to see what costs will be for different levels of activity, thus helping in planning.
d.It allows managers to develop financial results for a number of potential scenarios.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started