Question

1 Approved Answer

1. The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Costs Budgeted Costs Units produced 1,500 1,500 Direct

1.

The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows:

Actual Costs Budgeted Costs
Units produced 1,500 1,500
Direct materials cost $5,680 $5,010
Direct labor cost 1,620 1,420
VOH:
Maintenance 710 625
Power 300 190
FOH:
Grounds keeping 1,480 1,220
Depreciation 540 540

Calculate the flexible budget variance.

a.$110F

b.$1,065U

2.

c.$1,325U

d.$260F

Which of the following is true of an after-the-fact flexible budget?

a.It is a budget created in advance that is based on a particular level of activity.

b.It is used to compute what the costs should be for the level of output that actually occurred.

c.It allows managers to see what costs will be for different levels of activity, thus helping in planning.

d.It allows managers to develop financial results for a number of potential scenarios.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Other Assurance Services

Authors: Alvin Arens, James Loebbecke, W Lemon, Ingrid Splettstoesser

9th Canadian Edition

0130091243, 978-0130091246

More Books

Students also viewed these Accounting questions

Question

Why Security and Risk Management Matters ?

Answered: 1 week ago