1. The construction of a public facility costs $1,500,000 and annual maintenance cost is expected to be $10,000. At an effective annual interest rate of

image text in transcribed

1. The construction of a public facility costs $1,500,000 and annual maintenance cost is expected to be $10,000. At an effective annual interest rate of 10%, calculate the project's capitalized cost. (5 Points)