1. The difference between the actual time used and the amount of time that should have been used for actual production, multiplied by the standard
1. The difference between the actual time used and the amount of time that should have been used for actual production, multiplied by the standard labor rate per time is called
a. Efficiency variance
b. Price variance
c. Spending variance
d. Rate variance