Question
1. The formal acceptance of completed project deliverables occurs in which process in the 49-process framework? a. Validate scope b. Accept scope - Not correct
1. The formal acceptance of completed project deliverables occurs in which process in the 49-process framework? a. Validate scope b. Accept scope - Not correct c. Create WBS d. Control scope
2. The requirements management plan is an output of a. Collect requirements - not correct b. Define scope c. Plan scope management d. Control scope
3 . The stakeholder register is an input to which process? a. Plan scope management b. Define scope - not correct c. Control scope d. Collect requirements
4. Which of the following processes manages changes to the scope baseline? a. Perform integrated change control - Not correct b. Control scope c. Define scope d. Create WBS
5. The scope baseline can contain which of the following? a. WBS b. Detailed project requirements - Not correct c. Requirements traceability matrix d. Requirements management plan
Please help. Thank you in advance!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started