Question
1 Approved Answer
1. The process of manufacturing product ABC is: Torch Cut 47 minutes Deburr 7 minutes Drilling 31 minutes Tapping - 24 minutes Painting 14 minutes
1. The process of manufacturing product ABC is:
Torch Cut 47 minutes
Deburr 7 minutes
Drilling 31 minutes
Tapping - 24 minutes
Painting 14 minutes
Print Logos 5 minutes
but it takes (12) full days (3 shifts in a 24 hour/day operation) to complete the entire process. What is our in-process time ratio?
2. Total number of hours worked in the facility last month was 58,972. The Material Handling department worked 3240 hours. What is the Material Handling Ratio?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started