1. The Thoroughbred Consulting Group is designing a plant to produce a copper concentrate of 24.5% at 30 tons per hour. The mine produces average
1. The Thoroughbred Consulting Group is designing a plant to produce a copper concentrate of 24.5% at 30 tons per hour. The mine produces average ore grade is 0.9% at 2400 tons per hour. Determine the copper recovery from the proposed plant
Step by Step Solution
There are 3 Steps involved in it
Step: 1