Activity Duration (Days) Predecessor Activities
1. Reserve Church 1
2. Church Notice Wait 17 1. Resverve Church
3. Decorate Church 3 2. Church Notice Wait
4.Travel from Guatemala 10
5. Fit Dress 2 4.Travel from Guatemala
6. Choose Cake 2
7. Jack's Catering lead Time 10 6. Choose Cake
8. Rehearsal Dinner 1 "7. Jack's Catering lead Time 18 .Get Bridesmaids Gift "
9. Order and Receive Lace 8 10. Choose Pattern
10. Choose Pattern 3
11. Sew Dress 11 9. Order and Receive Lace
12. Clean and Press Dresses 2 5. Fit Dress
13. Order and Receive Invitations 12 14. Choose Invitations
14. Choose Invitations 3
15. Invitation Lead Time 10 16. Take to Post Office
16. Take to Post Office 1 17. Address Invitations
17. Address Invitations 4 "13. Order and Receive Invitations 19. Prepare Guest List "
18 .Get Bridesmaids Gift 1
19. Prepare Guest List 4
20. Wedding 1 "3. Decorate Church 8. Rehearsal Dinner 12. Clean and Press Dresses 15. Invitation Lead Time "
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started