1. Turn in a printed copy of the network 2. Turn in a printed bar chart of the project 3. How long in days, is

1. Turn in a printed copy of the network

2. Turn in a printed bar chart of the project

3. How long in days, is the critical path ?

Activity Duration (Days) Predecessor Activities

1. Reserve Church 1

2. Church Notice Wait 17 1. Resverve Church

3. Decorate Church 3 2. Church Notice Wait

4.Travel from Guatemala 10

5. Fit Dress 2 4.Travel from Guatemala

6. Choose Cake 2

7. Jack's Catering lead Time 10 6. Choose Cake

8. Rehearsal Dinner 1 "7. Jack's Catering lead Time 18 .Get Bridesmaids Gift "

9. Order and Receive Lace 8 10. Choose Pattern

10. Choose Pattern 3

11. Sew Dress 11 9. Order and Receive Lace

12. Clean and Press Dresses 2 5. Fit Dress

13. Order and Receive Invitations 12 14. Choose Invitations

14. Choose Invitations 3

15. Invitation Lead Time 10 16. Take to Post Office

16. Take to Post Office 1 17. Address Invitations

17. Address Invitations 4 "13. Order and Receive Invitations 19. Prepare Guest List "

18 .Get Bridesmaids Gift 1

19. Prepare Guest List 4

20. Wedding 1 "3. Decorate Church 8. Rehearsal Dinner 12. Clean and Press Dresses 15. Invitation Lead Time "

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Logistics

Authors: Paul R. Murphy, Michael Knemeyer

11th edition

132953463, 2900132953466, 978-0132953467

More Books

Students also viewed these General Management questions

Question

=+5.3. Show that m = E[ X ] minimizes E[(X- m)2].

Answered: 1 week ago