1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics

1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :

(i) Minimum Slack First

(ii) Shortest Job First

(iii) Maximum Resource Required First List the activities in the order in which you schedule them. Which activities are critical ? What is the Project Duration ? What is the efficiency of your schedule ?

ACTIVITY

DURATION

RESOURCE

1-2

3

2

1-3

4

3

1-4

2

1

2-5

2

2

2-6

5

2

3-7

3

1

4-7

1

3

4-8

4

2

5-9

1

1

6-7

2

4

6-9

4

2

7-10

3

4

8-10

2

1

9-10

3

5

Step by Step Solution

3.48 Rating (168 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics

Authors: Dean Karlan, Jonathan Morduch

1st edition

978-0077332587, 007733258X, 978-0077332648, 77332644, 978-1259163531

More Books

Students also viewed these Human Resource Management questions