1. Use the tables to answer a through e. Standard Cost Profile Lab Treatment SU #12 Expected Treatments = 1,000 Resource Quantity Variable Quantity Fixed
1. Use the tables to answer a through e.
Standard Cost Profile Lab Treatment SU #12 Expected Treatments = 1,000 | ||||||
Resource | Quantity Variable | Quantity Fixed | Unit Cost | Variable Cost | Average Fixed Cost | Average Total Cost |
Labor | 0.80 | 0.80 | $16.00 | $12.80 | $12.80 | $25.60 |
Supplies | 7.00 | 0 | 1.10 | 7.70 | 0 | 7.70 |
Total |
|
|
| $20.50 | $12.80 | $33.30 |
Actual Month Cost Lab Treatment SU #12 Actual Treatments = 1,100 | |||
Resource | Quantity Used | Unit Cost | Total Cost |
Labor | 1,600 | $17.00 | $27,200 |
Supplies | 7,500 | 1.00 | 7,500 |
Total |
|
| $34,700 |
Calculate the following variances:
a.Efficiency Variance Labor
b.Efficiency Variance Supplies
c.Price Variance Labor
d.Price Variance Supplies
e.Volume Variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started