Question

1 Approved Answer

1 . * * Value of waiting * * The project should either be started immediately or one year from now. NPV is 2 5

1.**Value of waiting**
The project should either be started immediately or one year from now. NPV is 25, and the initial expenditure for the project is 100. Risk-free rate: 5%. If the project is delayed by one year, there will be a relative loss of 40 in cash flow compared to starting it now, considering present value. However, the option values of waiting are inquired with given N(d1)=0.6~ and N(d2)=0.3~.
What is the option value of waiting?
Special Note:
1) For the convenience of calculations, the values of N(d1) and N(d2) were provided in this problem.
2) To facilitate calculations, the present value of the loss amount when the project is delayed (i.e., PV(div)) was given. Cf) Sx = S PV(div).
3) The question is not whether to wait or not for the project but rather inquires about the value of waiting.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Modelling Model Design And Best Practices Using Excel And VBA

Authors: Michael Rees

1st Edition

111890401X, 978-1118904015

More Books

Students also viewed these Finance questions