Question

1 Approved Answer

1. What is the optimum number of stations if you want to produce 4,500 PDAs per workday assuming 7.5 hours per day using these tasks?

1. What is the optimum number of stations if you want to produce 4,500 PDAs per workday assuming 7.5 hours per day using these tasks?

Work Task Time (seconds)
1 2.0
2 3.0
3 1.0
4 5.0
5 2.5
6 2.0
7 4.0
8 4.0
9 2.0
10 5.5
TOTAL 31 seconds

3.Compute efficiency of original line and the line you've assessed as optimum efficiency.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions