Question
1. Which of the following is not an input to the Conduct Procurements process? Group of answer choices Make-or-buy decisions Source selection WBS Organizational process
1. Which of the following is not an input to the Conduct Procurements process?
Group of answer choices
Make-or-buy decisions
Source selection
WBS
Organizational process assets
2. Which of these is not done during the Close Project process?
Group of answer choices
The handing over of deliverables to the receiving party.
Documenting the project learnings.
Release of project resources.
Creation of deliverables of the project.
3.Any numbering system that is used to monitor project costs by category such as labor, supplies, or materials, for example, is called
Group of answer choices
Standard accounting practices
Chart of accounts
Work breakdown structure
Universal accounting standard
4.All of the following are a type of project ending except for which one?
Group of answer choices
Extinction
Addition
Desertion
Starvation
5. What is critical path?
Group of answer choices
The path with the most activities with the longest durations.
The path with zero float.
The shortest path through the network, which represents the longest amount of time in which a project can be completed.
The longest path through the network, which represents the shortest amount of time in which a project can be completed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started