Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1) Which of the following is NOT part of the apportionment process? Apportionment Authorization Allotment Allocation 2) Which of the following is true concerning below-threshold

1) Which of the following is NOT part of the apportionment process?
Apportionment
Authorization
Allotment
Allocation
2) Which of the following is true concerning below-threshold reprogrammings in Research, Development, Test & Evaluation (RDT&E) appropriations? (Select one answer)
The amount added to an existing Project must be less than $2 million
The amount added to an existing Line Item must be less than $2 million
The amount added to an existing Budget Activity must be less than $10 million
The amount added to an existing Program Element must be less than $10 million
3) Time now is November 2014 (FY 15). Which of the following appropriations is CANCELLED at this time? Select all that apply. (Three correct answers)
FY 2007 Aircraft Procurement, Navy
FY 2008 RDT&E, Army
FY 2009 Operations & Maintenance, Army
FY 2008 Military Construction, Defense-Wide
4) All of the following may occur for acquisition programs whose actual obligations and expenditures appear to be significantly lower than their planned levels EXCEPT:
Have their budget requests for future years adjusted by Component or OSD budget analysts
Keep all or most of their funds by claiming that the variance is due to normal backlog at the government contracting officer
Have some or all of their available funds reprogrammed in the year of execution to meet other needs
Keep all or most of their funds if they can show that unusual problems are causing their actuals to appear lower than they really are
5) The Navy wants to move $5 million of aircraft procurement funds from the RAVEN aircraft line item to the KESTREL aircraft line item. Neither program is of special interest to Congress. This action requires:
Below-threshold reprogramming
Congressional notification reprogramming
Congressional prior approval reprogramming
Internal reprogramming
6) Your contractor complains that it has not been paid for an invoice submitted several months ago. Which one of the following is a potential cause of this problem?
Disbursing Office matches the certified contractor payment request up to one or more existing obligations in the accounting system.
Procuring Contracting Officer delayed award of the contract due to a protest
DFAS Regional Finance Center failed to submit a voucher summary to the Treasury
Items or services cited in the invoice could not be verified by the Administrative Contracting Officer
7) Which of the following information is NOT provided on the Contract Funds Status Report (CFSR)?
Amount obligated on the contract
Estimated termination costs
Earned Value to date by Work Breakdown Structure element
Forecast of billings to the government
8) Obligation and expenditure plans:
Should always be coordinated with the regional Defense Finance and Accounting Service (DFAS) office
Are prepared by the Program Management Offices
Should include as many fourth-quarter obligations and expenditures as possible to minimize the possibility of falling behind the execution plan
Should reflect the most optimistic schedule for executing funds
9) $150,000 was committed in February for a research and development contract to be awarded in May. Unfortunately, the lowest bid received by the Procuring Contracting Officer was $200,000. According to the rules governing commitments: (select one)
A new commitment for an additional $200,000 should be recorded
The official who authorized the original commitment need not take any action
The original commitment amount must be increased to $200,000 before the obligation can be recorded
The $200,000 obligation for the contract award can be recorded without adjusting the original commitment amount
10) Which of the following is a temporary impoundment of funds?
Deferral
Commitment
Rescission
Offset
11) Reimbursable orders are recorded as obligations when: (select one)
The providing activity accepts the order in writing
The providing activity performs the work or delivers the product ordered
The ordering activity delivers the order to the providing activity
The providing activity awards a contract to a third party to perform the work ordered
12) An operational Navy base used $150,000 of FY 2015 Operations and Maintenance (O&M) funds to award a janitorial contract covering the period June 2015 through October 2015. Assuming that janitorial contracts on this base are ordinarily financed with O&M funds, this action most likely: (select one)
Violated the Misappropriation Act
Violated the Antideficiency Act
Did not violate any fiscal laws
Violated the Bona Fide Need Rule
13) The unliquidated balance of a cancelled appropriation: (select one answer only)
May be used to make new obligations
May not be used to pay any bills
Is added to a merged account

May be used to pay bills on the original obligation

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multinational Financial Management

Authors: Alan C Shapiro, Paul Hanouna

11th Edition

1119559901, 9781119559900

More Books

Students also viewed these Finance questions

Question

4. What means will you use to achieve these values?

Answered: 1 week ago