1 You encounter a problem that requires changes to the project plan your stakeholders agreed upon. Which of the following is the best choice for
1 You encounter a problem that requires changes to the project plan your stakeholders agreed upon. Which of the following is the best choice for how to address the problem? 1 point Challenge your team members to do better and reward improved performance. Pause operations until your stakeholders address the problem. Present the problem succinctly to your stakeholders and offer a solution. Present all the relevant project documents and send an email to your stakeholders