Question
10. Pick three tasks that can be delegated from the following list: a. Evaluations b. Routine tasks for you c. Everything d. Tasks requiring technical
10. Pick three tasks that can be delegated from the following list:
a. Evaluations
b. Routine tasks for you
c. Everything
d. Tasks requiring technical expertise
e. Enjoyable tasks
f. Personal tasks
g. Confidential
h. Crises
i. Cross-training
11. Pick three tasks that should NOT be delegated from the following list:
a. Evaluations
b. Routine tasks for you
c. Everything
d. Tasks requiring technical expertise
e. Enjoyable tasks
f. Personal tasks
g. Confidential
h. Crises
i. Cross-training
12. A deliverable is?
a. Outside the project scope.
b. A product produced as part of the project.
c. Not produced during the project.
d. Software or hardware only.
13. You may be working for multiple bosses in this organizational structure:
a. Project
b. Functional
c. Matrix
d. None of the above
14. A project manager's most important job is to?
a. Develop the project plan
b. Treat everyone with dignity and respect
c. Track the project budget
d. Manage the project change control process
e. All of the above
15. Three primary methods for determining the projected financial value of projects are?
a. WBS, SOW, and NPV.
b. NPV, SOW, and SWOT.
c. NPV, ROI, and Payback Period.
d. PMI, ASPCA and OMDB. The choice of contract type directly affects the level of risk to both buyer and seller.
16. What contract type typically entails the most risk to a buyer?
17. What contract type typically entails the least risk to a buyer?
18. Project recovery techniques call for creating a mini-project to return the project to the original or baseline plan. True or False?
19. An approach you can use to develop a good WBS is?
a. Top-down.
b. Bottom-up.
c. Analogy.
d. All of the above.
20. The basis for creating a project schedule includes?
a. Activity definition
b. Critical path analysis
c. Activity duration estimating
d. All of the above
21. The shortest time it takes to complete the project is?
a. Established by summary milestones.
b. Found with the forward pass calculations.
c. Does not change during the project execution.
d. Found on the critical path.
22. Budgeted cost of work performed is?
a. Unencumbered costs.
b. Total of direct and indirect actual costs in a given time period.
c. Percent of work planned in a given time period.
d. Earned value.
23. If a project has an SPI of 110% and a CPI of 95%, it is:
a. Over budget, behind schedule
b. Under budget, behind schedule
c. Over budget, ahead of schedule
d. Under budget, ahead of schedule .
24. Behavioral theory useful to project managers includes all the following except:
a. Mazlow
b. Herzberg
c. Litmus test
d. Theory X and Y
e. Hawthorne effect
f. MBTI
How many project managers does it take to change a light bulb, and why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started