Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

10. The SMAW equipment in the case study can be purchased for a fixed cost of $12,000, and it costs $30/hour to run the process.

image text in transcribed
image text in transcribed
10. The SMAW equipment in the case study can be purchased for a fixed cost of $12,000, and it costs $30/hour to run the process. The automated FCAW equipment costs $25,000 to purchase and $36/hour to run. At what level of planned production volume would it make sense to implement the FCAW process rather than SMAW? Welding Case Study: Steel Wall Support Panels in North Carolina A small start-up company has developed in central North Carolina to take advantage of the relatively strong market there for low-cost, manufactured homes. The company has researched and prototyped several types of structural wall support panels made from cold rolled, medium- carbon steel that can outperform wood construction methods in terms of performance and cost. The prototype panels are made of two separate steel components joined along one side. The prototype assemblies were constructed using threaded fasteners since they are cheap and the designers frequently needed to disassemble the panels as the design requirements changed. Now, however, the panel design has matured to a well-defined product. To produce dozens of identical panels, the group has planned an arc welding process to add fillet welds along both sides of the overlapping components. Although the design of the steel components includes a number of pockets and cutouts to reduce weight, a simplified cross-section of the assembly arrangement is shown in the figure below. A manual stick welding (SMAW) process is used for the welds. The time to complete one 2- meter long panel section is determined by the 100 A power supply (operated at 20 V), the steel alloy used (its melting factor is typically approximated by 0.55), and the size of the components (each is 12 mm thick). Each of the two weld seams has approximately 72 mm cross section. The company welders typically achieve an arc time proportion of 25% of total work time. Production numbers for the panels are expected to ramp up into hundreds or even thousands in the near future. A more automated welding solution is proposed in the form of flux-cored are welding (FCAW). With the continuously fed electrode of FCAW, a higher current of 200 A can be used, and mechanized control of motion will increase the are time to 50%. The automated solution, of course, requires a higher initial investment. 10. The SMAW equipment in the case study can be purchased for a fixed cost of $12,000, and it costs $30/hour to run the process. The automated FCAW equipment costs $25,000 to purchase and $36/hour to run. At what level of planned production volume would it make sense to implement the FCAW process rather than SMAW? Welding Case Study: Steel Wall Support Panels in North Carolina A small start-up company has developed in central North Carolina to take advantage of the relatively strong market there for low-cost, manufactured homes. The company has researched and prototyped several types of structural wall support panels made from cold rolled, medium- carbon steel that can outperform wood construction methods in terms of performance and cost. The prototype panels are made of two separate steel components joined along one side. The prototype assemblies were constructed using threaded fasteners since they are cheap and the designers frequently needed to disassemble the panels as the design requirements changed. Now, however, the panel design has matured to a well-defined product. To produce dozens of identical panels, the group has planned an arc welding process to add fillet welds along both sides of the overlapping components. Although the design of the steel components includes a number of pockets and cutouts to reduce weight, a simplified cross-section of the assembly arrangement is shown in the figure below. A manual stick welding (SMAW) process is used for the welds. The time to complete one 2- meter long panel section is determined by the 100 A power supply (operated at 20 V), the steel alloy used (its melting factor is typically approximated by 0.55), and the size of the components (each is 12 mm thick). Each of the two weld seams has approximately 72 mm cross section. The company welders typically achieve an arc time proportion of 25% of total work time. Production numbers for the panels are expected to ramp up into hundreds or even thousands in the near future. A more automated welding solution is proposed in the form of flux-cored are welding (FCAW). With the continuously fed electrode of FCAW, a higher current of 200 A can be used, and mechanized control of motion will increase the are time to 50%. The automated solution, of course, requires a higher initial investment

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting The Impact On Decision Makers

Authors: Gary A Porter, Curtis L Norton

8th Edition

1111534861, 9781111534868

More Books

Students also viewed these Finance questions

Question

Importers who pay for goods using foreign currencies. LO.1

Answered: 1 week ago