Question
11. In which method does the owner enter into only one contract for both the design and construction? Group of answer choices General contract (DBB)
11. In which method does the owner enter into only one contract for both the design and construction?
Group of answer choices
General contract (DBB)
Separate contracts
CM/GC
Design-build
12. Which method is not suited for fast-tracking?
Group of answer choices
CM/GC
Integrated Project Delivery
Design-build
General contract (DBB)
13. Which of the following indicates several liability?
Group of answer choices
Each party agrees to the basic meaning and legal implications of the contract.
The terms of the agreement are not clearly stated but are established through inference and deduction by one party.
Each individual involved in the contract has liability that is separate from the others.
Subject matter cannot violate any fundamental dictates of common law.
A promise is made by only one party to the contract.
14. Which of the following is an example of force majeure?
Group of answer choices
An owner claiming the rights to the design of a project.
Giving Subcontractor A the quotes submitted by other subcontractors so that Subcontractor A can lower its bid.
Putting all of the risk for construction means and methods on the architect.
Forgetting to multiply by 12 to convert from feet to inches when estimating the cost of a project.
An earthquake.
15. When a party in a contract fails to fulfill a promise made in the contract, that party has _____________ the contract.
Group of answer choices
Assigned
Novated
Executed
Privity of
Breached
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started