Question
11. Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 23 direct labor-hours at $15 per direct labor-hour. During a
11. Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 23 direct labor-hours at $15 per direct labor-hour. During a recent period 1,450 cranes were made. The labor rate variance was zero and the labor efficiency variance was $5,400 unfavorable. How many actual direct labor-hours were worked? |
38,750
33,350
33,710
31,900
12.
Munar Corporation uses activity-based costing to compute product margins. Overhead costs have already been allocated to the company's three activity cost pools-Machining, Order Filling, and Other. The costs in those activity cost pools appear below: |
Machining | $10,224 |
Order Filling | $24,282 |
Other | $6,900 |
Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. Activity data appear below: |
| MHs (Machining) | Orders (Order Filling) |
Product Z3 | 3,300 | 240 |
Product X6 | 10,900 | 1,180 |
Finally, sales and direct cost data are combined with Machining and Order Filling costs to determine product margins. |
| Product Z3 | Product X6 |
Sales (total) | $92,100 | $98,600 |
Direct materials (total) | $42,800 | $32,000 |
Direct labor (total) | $36,100 | $37,200 |
What is the overhead cost assigned to Product X6 under activity-based costing? (Round the Intermediate calculation to two decimal places and your final answer to nearest whole dollar.) |
$14,900
$7,848
$20,178
$28,026
13.
Brisky Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing system allocates two overhead accounts-equipment depreciation and supervisory expense-to three activity cost pools-Machining, Order Filling, and Other-based on resource consumption. Data to perform these allocations appear below: |
Overhead costs: |
|
Equipment depreciation | $30,000 |
Supervisory expense | $14,800 |
Distribution of Resource Consumption Across Activity Cost Pools: | |||
| Activity Cost Pools | ||
| Machining | Order Filling | Other |
Equipment depreciation | 0.50 | 0.40 | 0.10 |
Supervisory expense | 0.50 | 0.30 | 0.20 |
In the second stage, Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. |
Activity: |
|
|
| MHs (Machining) | Orders (Order Filling) |
Product I3 | 5,530 | 161 |
Product U8 | 17,000 | 964 |
Total | 22,530 | 1,125 |
Finally, sales and direct cost data are combined with Machining and Order Filling costs to determine product margins. |
Sales and Direct Cost Data: |
|
|
| Product I3 | Product U8 |
Sales (total) | $69,700 | $65,700 |
Direct materials (total) | $31,100 | $23,900 |
Direct labor (total) | $22,400 | $29,500 |
What is the product margin for Product I3 under activity-based costing? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.) |
$1,067
$8,373
$9,153
$12,933
14.
The Wright Company has a standard costing system. The following data are available for September: |
Actual quantity of direct materials purchased | 30,000 | pounds |
Standard price of direct materials | $5 | per pound |
Material price variance | $3,000 | unfavorable |
Material quantity variance | $2,000 | favorable |
The actual price per pound of direct materials purchased in September is: (Round your answer to 2 decimal places.) |
$4.86
$5.00
$5.10
$5.14
15.
Avril Company makes collections on sales according to the following schedule: |
30% in the month of sale |
64% in the month following sale |
6% in the second month following sale |
The following sales have been are expected: |
| Expected Sales |
January | $100,000 |
February | $110,000 |
March | $100,000 |
Budgeted cash collections in March should be budgeted to be: |
$100,000
$106,400
$100,600
$100,400
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started