12. Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Data relating to the construction
12. Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Data relating to the construction are: Costs to date 2010, $1,650,000 2011, $3,025,000 Estimated costs to complete 2010, 1,350,000 zero 2011 Dalton uses the percentage-of-completion method. How much revenue should be reported for 2010?* (2 Points) The value must be a number