12 of 21 In the project Brook is managing, a short and very important activity is scheduled to occur midway through a long activity. The
12 of 21 In the project Brook is managing, a short and very important activity is scheduled to occur midway through a long activity. The same resource is assigned to both. Which type of adjustment works best to resolve the overallocation in this situation? Select an answer: delaying replacing resources splitting fast-tracking