12-2) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount

12-2)

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount on Hand Direct Components
End 1 L(2), C(1), K(3)
L 2 10 B(2), J(3)
C 3 15 G(2), B(2)
K 3 20 H(4), B(2)
B 2 30
J 3 30
G 3 5
H 2

a.

If 42 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You dont need to develop an MRP plan.)

Additional units

b.

An order for the end item is scheduled to be shipped at the start of week 8. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You dont need to develop an MRP plan.)

The latest week

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: John J. Wild, Ken W. Shaw

2010 Edition

978-0073379586

Students also viewed these Accounting questions