12...For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements

12...For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?

The activity is on the critical path.

The early finish is 10.

The slack for this activity is 2.

The duration of this activity is 2.

The late finish is 12.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Environmental Accounting Issues Concepts And Practice

Authors: Stefan Schaltegger, Roger Burritt

1st Edition

1874719349, 9781874719342

More Books

Students also viewed these Accounting questions

Question

Describe the goal of cognitive psychotherapy.

Answered: 1 week ago

Question

How do you add two harmonic motions having different frequencies?

Answered: 1 week ago

Question

2. Develop a good and lasting relationship

Answered: 1 week ago

Question

1. Avoid conflicts in the relationship

Answered: 1 week ago