Question
1 Approved Answer
13 options: 1. Project C Data Task Duration (Days) Predecessor(s) $Budget Staus at the end of day 23 B 8 Start 4,000 Completed and spent
13 options: 1. Project C Data Task Duration (Days) Predecessor(s) $Budget Staus at the end of day 23 B 8 Start 4,000 Completed and spent 5,000 A 8 B(FS+3) 3,000 Completed and spent 2,000 E 8