14. A project's budget of $7,000 is determined to have too many errors to continue with it. An independent estimate of the remaining work is

image text in transcribed
14. A project's budget of $7,000 is determined to have too many errors to continue with it. An independent estimate of the remaining work is $3,000. $1,000 has already been spent. What is the Estimate at Completion for the project? (4 points)