14 Gold Company uses a plantwide overhead rate with machine hours as the allocation base. Use the following Information to solve for the amount of machine hours estimated per unit of product RST 1 points Direct material cost per unit of RST Total estimated manufacturing overhead Total cost per unit of RST Total estimated machine hours Direct labor cost per unit of RST $ 22 $471,000 $ 87 157,000 MH $ 30 8 01:36:22 Multiple Choice 11.67 MH per unit of RST O 3.00 MH per unit of RST 3263 MH per unit of RST 50.67 MH per unit of RST 52.00 MH per unit of RST O 15 Part 1 of 2 Required Information [The following information applies to the questions displayed below) Aztec Industries produces bread which goes through two operations, mixing and baking, before it is ready to be packaged. Next year's expected costs and activities are shown below. Mixing Baking Direct labor hours 407,000 DLH 87,800 DLH Machine hours *807,000 MH 807,000 MH Overhead costs $569,800 $407,600 1 points 01:35:57 Compute Aztec's departmental overhead rate for the baking department based on direct labor hours. Multiple Choice $4.68 per DLH $1.40 per DLH O $0.71 per DLH o $0.50 per DLH $198 per DLH 16 Required Information [The following information applies to the questions displayed below) Part 2 of 2 Aztec Industries produces bread which goes through two operations, mixing and baking, before it is ready to be packaged. Next year's expected costs and activities are shown below. 1 points Direct labor hours Machine hours Overhead costs Mixing 407,000 DLH "807,00 MH $569,800 Baking 87,000 DLH 807,000 MH $407, see 8 01:35:35 Compute Aztec's departmental overhead rate for the baking department based on machine hours Multiple Choice $1.40 per MH O $4.68 per MH $0.71 per MH O $0.50 per MH $1.98 per MH 17 A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Product A Product B Product C 1 points Activity Cost Pool Activity 1 Activity 2 Activity 3 Budgeted Cost $ 85,000 $ 60,000 $112.000 7,500 8,500 4,000 10,500 16,500 2,500 21,500 9,500 3,125 8 01:35:13 Which of the following statements is true regarding this company's activity rates? Multiple Choice o The activity rate under the activity-based costing system for Activity 2 is $215. O The activity rate under the activity-based costing system for Activity 2 is $11.64. The activity rate under the activity based costing system for Activity 2 is $174 The activity rate under the activity-based costing system for Activity 2 is $15.53 O The activity rate under the activity-based costing system for Activity 2 is $3.42