Question

1 Approved Answer

14. what is the minimum cost of crashing the following project by one day? Activity Immediate Predecessor Normal Time Normal Cost Crash Time Crash Cost

14. what is the minimum cost of crashing the following project by one day?

Activity

Immediate

Predecessor

Normal TimeNormal CostCrash TimeCrash Cost
A-6 days$9005 days$1000
B-8 days$3006 days$400
C-4 days$5003 days$600
DA5 days$9003 days$1200
EC8 days$10005 days$1600

A) $50

B) $100

C) $150

D) $200

E) $1100

15. Based on the manufacturing process describe in this diagram what is the pace of the process:

image text in transcribed
23 min/unit 84min/unit 84min/unit 27 min/unit 84 min/unit 20 min/unit .' welding 25 min/unit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management

Authors: Alexander Chernev

3rd Edition

193657263X, 9781936572632

More Books

Students also viewed these General Management questions