14. what is the minimum cost of crashing the following project by one day?
Activity | Immediate Predecessor | Normal Time | Normal Cost | Crash Time | Crash Cost |
A | - | 6 days | $900 | 5 days | $1000 |
B | - | 8 days | $300 | 6 days | $400 |
C | - | 4 days | $500 | 3 days | $600 |
D | A | 5 days | $900 | 3 days | $1200 |
E | C | 8 days | $1000 | 5 days | $1600 |
A) $50
B) $100
C) $150
D) $200
E) $1100
15. Based on the manufacturing process describe in this diagram what is the pace of the process:
23 min/unit 84min/unit 84min/unit 27 min/unit 84 min/unit 20 min/unit .' welding 25 min/unitStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started