155 of 175 For a particular project, it is estimated that a 20,000 LF, 4-way, concrete encased duct-bank is to be installed. The budgeted production

image text in transcribed
image text in transcribed
155 of 175 For a particular project, it is estimated that a 20,000 LF, 4-way, concrete encased duct-bank is to be installed. The budgeted production crew rate is 8 hours per 300 LF and at a cost of $250 per 100 LF. During a reporting period, 60% of the duct-bank has been installed and 300 crew hours have been expended at a cost of $30,000. What is the schedule variance? Assume behind schedule is a negative (-). 30 20 For 1 paine

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tourism Concepts And Practices

Authors: John R Walker, Josielyn T Walker

1st Edition

0138142459, 9780138142452

More Books

Students also viewed these General Management questions

Question

Relax your shoulders

Answered: 1 week ago