Question
(17) The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.91; actual, $2.05 Yards per unit: standard, 4.64 yards;
(17) The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.91; actual, $2.05 Yards per unit: standard, 4.64 yards; actual, 5.26 yards Units of production: 9,300 The direct materials quantity variance is
a.$11,013.06 unfavorable
b.$11,820.30 favorable
c.$11,013.06 favorable
d.$11,820.30 unfavorable
(18) The following data relate to direct labor costs for the current period:
Standard costs | 6,800 hours at $11.80 |
Actual costs | 6,400 hours at $10.80 |
The direct labor rate variance is
a.$11,120 unfavorable
b.$6,400 favorable
c.$11,120 favorable
d.$4,720 favorable
Standard | Actual | |
Variable overhead rate | $3.35 | |
Fixed overhead rate | $1.80 | |
Hours | 18,900 | 17,955* |
Fixed overhead | $46,000 | |
Actual variable overhead | $67,430 | |
Total factory overhead | $101,450 |
*Actual hours are equal to standard hours for units produced.
The variable factory overhead controllable variance is
a.$7,280.75 favorable
b.$7,280.75 unfavorable
c.$8,981.75 unfavorable
d.$8,981.75 favorable
(20) The standard costs and actual costs for direct materials for the manufacture of 2,300 actual units of product are as follows:
Standard Costs | |
Direct materials | 1,040 kilograms at $8.85 |
Actual Costs | |
Direct materials | 2,300 kilograms at $8.40 |
The direct materials price variance is
a.$1,035 unfavorable
b.$468 favorable
c.$468 unfavorable
d.$1,035 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started