18. A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C A 4
18. A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C A 4 D B,C 8 Table YY Using Table YY, the time to complete the entire project would be a) 23 days. b) 19 days. c) 17 days. d) 11 days. Ans_____