Question

1 Approved Answer

#18. LM Inc. manufactures air filters used in lawn mowers. The demand for these filters 6,480 units per week. LMs available productive time is 90

#18. LM Inc. manufactures air filters used in lawn mowers. The demand for these filters 6,480 units per week. LMs available productive time is 90 hours per week based on two shifts, six days per week. The filter production is completed in four work cells and the production time per work cell is as follows:

work cell cycle time
cell 1 90 seconds
cell 2 125 seconds
cell 3 105 seconds
cell 4 75 seconds

a. Calculate the Takt Time in seconds.

b. Calculate the total cycle time in seconds?

c. How many employees are needed for the production process?

d. What is the key driver of Takt Time: production or demand? (Circle the correct answer.) e. What is the strategic role of Takt Time in an organization? Explain why you think this is strategic.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Financial & Managerial Accounting, The Financial Chapters

Authors: Tracie Miller Nobles, Brenda Mattison

7th Edition

0136505279, 9780136505273

More Books

Students also viewed these Accounting questions