19. A labor efficiency variance resulting from the use of poor-quality materials should be charged to A) the production manager. B) the purchasing agent. C)
19. A labor efficiency variance resulting from the use of poor-quality materials should be charged to
A) the production manager.
B) the purchasing agent.
C) manufacturing overhead.
D) the marketing department.
Breifly explain