19-1B Rothchild Company Journal Enteries Date Particulars Debit in $ Credit in $ 4-Aug Materials 168000 Accounts Payable 168000 12000X14 24-Aug Work in Progress 126800
19-1B | |||||
Rothchild Company | |||||
Journal Enteries | |||||
Date | Particulars | Debit in $ | Credit in $ | ||
4-Aug | Materials | 168000 | |||
Accounts Payable | 168000 | ||||
12000X14 | |||||
24-Aug | Work in Progress | 126800 | |||
Materials | 126800 | ||||
Job 40 (5000X8) | 40000 | ||||
Job 42 (6200X14) | 86800 | ||||
Total | 126800 | ||||
19-2B | |||||
Journal Enteries | |||||
Date | Particulars | Debit in $ | Credit in $ | ||
Work in Progress | 186200 | ||||
Wages Payable | 186200 | ||||
Job 40 (3500x25) | 87500 | ||||
Job 42 (4200x23.50) | 98700 | ||||
Total | 186200 |
PE 19 - 4B
a) Predetermine overhead rate = Overhead / Direct labour hours = 810000 / 90000 = $9 per hour
b) Overhead to be charge on Jobs = No. oh hours worked * Overhead Rate
Job 40 = 3500 * 9 = $31500
Job 42 = 4200 * 9 = $37800
Total Overhead = $69300
c) Work in Progress A/c Dr. 69300
To Factory Overhead A/c 69300
(Being Factory overhead charge on the basis of predetermine rate of overhead)
Example Exercise 19-5 Job Costs Obj. 2 At the end of March, Hatch Company had completed Jobs 101 and 102. Job 101 is for 500 units, and Job 102 is for 1,000 units. Using the data from Example Exercises 19-1, 19-2, and 19-4, determine (a) the balance on the job cost sheets for Jobs 101 and 102 at the end of March and (b) the cost per unit for Jobs 101 and 102 at the end of March Follow My Example 19-5 a. Job 101 Direct materials $ 2,400 Direct labor 12,800 Factory overhead 3,200 Total costs $18,400 Job 101 $36.80 = $18,400 = 500 units Job 102 $13.80 = $13,800 - 1,000 units Job 102 $ 4,200 7,200 2,400 $13,800 b. EE 19-5 p.937 PE 19-5B Job costs OBJ. 2 At the end of August, Rothchild Company had completed Jobs 40 and 42. Job 40 is for 10,000 units, and Job 42 is for 11,000 units. Using the data from Practice Exercises 19-1B, 19-2B, and 19-4B, determine (a) the balance on the job cost sheets for Jobs 40 and 42 at the end of August and (b) the cost per unit for Jobs 40 and 42 at the end of AugustStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started