19b - StarBuilder just completed a project at a final cost of $220k. The CPIF contract states the following: Target cost = $250k, Target fee
19b - StarBuilder just completed a project at a final cost of $220k. The CPIF contract states the following: Target cost = $250k, Target fee = $20k, Max fee = $40k, Min fee = $10k, and any cost savings will be shared equally between buyer and contractor. How much should StarBuilder expect to get paid?