Question
19).Job Y3K incurred the following: $15,500 direct material, $17,700 direct labor, 900 machine hours and 600 labor hours. The company uses a single plant-wide overhead
19).Job Y3K incurred the following: $15,500 direct material, $17,700 direct labor, 900 machine hours and 600 labor hours. The company uses a single plant-wide overhead rate based on labor hours. The overhead rate is $11.50 per labor hour. What is the total cost for job Y3K?
a).$40,100 b).$43,550 c).$39,900 d).$50,450
20).Job Y3K incurred the following: $15,500 direct material, $17,700 direct labor, 900 machine hours and 600 labor hours. The company uses a single plant-wide overhead rate based on labor hours. The overhead rate is $11.50 per labor hour. Job Y3K consisted of 1,200 units. What is cost per unit for job Y3K?
a).$33.42 b).$36.29 c).$33.25 d).$42.04
21).Estimates: 30000 labor hours; 1400 machine hours; $55000 fixed overhead; $7 variable overhead per machine hour. What is the predetermined overhead rate with machine hours as the allocation base?
a).$46.29 b).$7.15 c).$10.98 d).$8.97
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started