1.A company is considering 3 investments with the measures below. Which measure should they use to select their top choice if the only priority is the best return on their investment? Using that measure, select the investment that would be their top choice and enter as your answer.
Investment required | NPV | Project profitability | |
Project T | 82510 | 6863 | 1.87 |
Project N | 30019 | 3657 | 2.73 |
Project R | 60365 | 5959 | 1.49 |