Question

1 Approved Answer

1.ABC planned to produce 9,000 units, but actually produced 10,000 units.Each unit has a standard quantity of 5lb of material, and a standard price for

1.ABC planned to produce 9,000 units, but actually produced 10,000 units.Each unit has a standard quantity of 5lb of material, and a standard price for the material of $8 per pound.ABC purchased 55,000lb of material (at $10 per pound) but only used 45,000lb.

a.What is the material quantity variance?

b. What is the material price variance?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, G. Richard Chesley, Ray Carroll

6th Canadian Edition

0070915164, 9780070915169

More Books

Students also viewed these Accounting questions

Question

1. Maintain my own perspective and my opinions

Answered: 1 week ago