1.Given the information in the following table, draw the AOA network. a.Develop the appropriate AON network b.Find the critical path and critical time for the
1.Given the information in the following table, draw the AOA network.
a.Develop the appropriate AON network
b.Find the critical path and critical time for the network.
c.Then find the slack for all activities.
Step by Step Solution
There are 3 Steps involved in it
Step: 1