1)If a company took 100 hours to assemble their first unit and 90 hours to assemble the second unit, we might expect it to take:
1)If a company took 100 hours to assemble their first unit and 90 hours to assemble the second unit, we might expect it to take:
72.25 hours to assemble the fourth unit.
70 hours to assemble the third unit.
72.25 hours to assemble the third unit.
81 hours to assemble the fourth unit.
2)It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 92% unit learning curve. Estimate the cost of the 10th unit. (Round intermediate calculations to 4 decimal places)
$15,661
$10,380
$9,665
$11,985
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started