1.Mass Balance Company is manufacturing a new digital scale for use by a large chemical company.The order is for 40 units.The first scale took 60
1.Mass Balance Company is manufacturing a new digital scale for use by a large chemical company.The order is for 40 units.The first scale took 60 hours of direct labor.The second unit took 54 hours to complete.
What is the average time per unit for producing the last 10 units (#31 - #40)?