Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1.Project Activity List, Task Relationships, & Estimated Durations Using the work breakdown structure (WBS)provided(See TableTwo-Example Project Information for Schedule Network Diagram)use the Program Evaluation and

1.Project Activity List, Task Relationships, & Estimated Durations Using the work breakdown structure (WBS)provided(See TableTwo-Example Project Information for Schedule Network Diagram)use the Program Evaluation and Review Technique (PERT) to calculate the Triangular and Betaestimates using the optimistic, most likely, and pessimistic estimated durations 2.Schedule Network Diagram Large and complex projectsare difficult to create full schedule network diagrams, so we'll use a example project for this part of the project.The activity list, predecessors, and estimated durations for this part of the assignment are listed in the table. Please use MicrosoftWord tocreate a schedule network diagram for the example project.

3.Critical Path using the completed schedule network diagram (from item #2 above), identify which tasks are on the critical path for the example project. List the tasks on the critical path.

1.Completed Activity List & Estimated Durationsfor the WBS(refer to Table One-EstimatedDurations).

2.Schedule Network Diagram for the example project(refer to Table Two-Example ProjectInformation for Schedule Network Diagram).

3.Summary of the critical path for the example project(refer to Table Two-Example ProjectInformation for Schedule Network Diagram)

Table one- Estimated Durations

Activity

Optimistic Most Likely Pessimistic PERT Estimate-Triangular Distribution PERT Estimate-Beta Distribution
1 2 4 6
2 1 4 5
3 3 7 8
4 1 5 8
5 2 3 8
6 3 4 7
7 2 7 9
8 5 7 11
9 2 3 6
10 1 5 6

Table Two- Example project information for schedule Network Diagram

PERT Estimate Calculation

WBS ID Activity Name Predecessors Estimated Duration Optimistic Time Most likely Time Pessimistic time
1.1 Activity A - 4.0 2 4 6
1.2 Activity B 1.1 2.8 1 3 4
1.3 Activity C 1.2 10.3 7 10 15
1.4 Activity D 1.3 6.2 5 6 8
1.5 Activity E 1.1 12.2 10 12 15
2.1 Activity F 1.1 6.0 4 6 8
2.2 Activity G 2.1 8.2 6 8 11
2.3 Activity H 1.5, 2.2 9.3 8 9 12
2.5 Activity I 2.2 4.2 2 4 7
2.6 Activity J 1.4, 2.3, 2.5 2.8 1 3 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Alice R. O'Grady

9th Edition

0205627730, 978-0205627738

More Books

Students also viewed these General Management questions

Question

=+2 Identify the treatment and response.

Answered: 1 week ago