Question
1.Resource leveling or smoothing can have all the following results on a project EXCEPTSingle choice. (1 Point) Lower peak resource demand. Reduced resource need A
1.Resource leveling or smoothing can have all the following results on a project EXCEPTSingle choice.
(1 Point)
Lower peak resource demand.
Reduced resource need
A longer project duration
2.All of the following are types of resource constraints EXCEPTSingle choice.
(1 Point)
Material
People
Equipment
Information
3.When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is calledSingle choice.
(1 Point)
Outsourcing
Redistribution of projects
Project allocation
Task sharing
4.In a resource-constrained project, which of the following is most likely to be changed?Single choice.
(1 Point)
The completion date
The budget
Project quality
Resource levels
5.Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resourceSingle choice.
(1 Point)
Shifting
Manipulating
Smoothing
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
The detailed answer for the above question is provided below 1 Resource leveling or smoothing can have all the following results on a project EXCEPT A ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started