Question

00
1 Approved Answer

1.)The base cost of the project is $200,000, Assume the original profit margin is $20,000 ( i.e. 10%). Therefore, the total bid is $220,000. The

1.)The base cost of the project is $200,000, Assume the original profit margin is $20,000 ( i.e. 10%). Therefore, the total bid is $220,000. The owner retains 10% of all validated progress payment claims until one half of the contract value ( $110,000*0.10) has been built, and accepted as complete. The progress payments will be billed at the end of month. The owner will transfer the billed amount minus any retainage to the contractor 30 days later. The interest on overdraft is 1% per month.

The amount of each progress payment is given in chart as follows:

How much is the payment is received by contractor at the beginning of month 3 ?

Month 1 month 2 month 3 month 4 month 5 month 6 Direct cost $25000 $65000 $75000 $15000 Indirect cost $5000 $5000 $5000 $5000

subtotal

Markup

Total Billed

Retainage withheld

Payment received

Total cost to date

Total amount billed to date

Total paid to date

Overdraft end of month

interest on overdraft balance

Total amount financed

Group of answer choices

a). 300

b). 1103

c). none of these answers

d). 29,700

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions