Question
1.)The base cost of the project is $200,000, Assume the original profit margin is $20,000 ( i.e. 10%). Therefore, the total bid is $220,000. The
1.)The base cost of the project is $200,000, Assume the original profit margin is $20,000 ( i.e. 10%). Therefore, the total bid is $220,000. The owner retains 10% of all validated progress payment claims until one half of the contract value ( $110,000*0.10) has been built, and accepted as complete. The progress payments will be billed at the end of month. The owner will transfer the billed amount minus any retainage to the contractor 30 days later. The interest on overdraft is 1% per month.
The amount of each progress payment is given in chart as follows:
How much is the payment is received by contractor at the beginning of month 3 ?
Month 1 month 2 month 3 month 4 month 5 month 6 Direct cost $25000 $65000 $75000 $15000 Indirect cost $5000 $5000 $5000 $5000
subtotal
Markup
Total Billed
Retainage withheld
Payment received
Total cost to date
Total amount billed to date
Total paid to date
Overdraft end of month
interest on overdraft balance
Total amount financed
Group of answer choices
a). 300
b). 1103
c). none of these answers
d). 29,700
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started