1.The following task must be performed on an assembly in the sequence and times specified; Task Task time (in second) Task that precedes A 50
1.The following task must be performed on an assembly in the sequence and times specified;
Task
Task time (in second)
Task that precedes
A
50
-----
B
40
-----
C
20
A
D
45
C
E
20
C
F
25
D
G
10
E
H
35
B, F, G
Required;
a.Draw the schematic diagram
b.What is the theoretical minimum number of stations required to meet a forecast demand of 400 units per eight hour day?
c.Use the longest task time and balance the line in the minimum number of stations to produce 400 units per day.
d.Calculate efficiency of the line.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started