Question
1.The procurement phase precedes the design phase since it involves the bidding and award of architect services. Group of answer choices True False 2. A
1.The procurement phase precedes the design phase since it involves the bidding and award of architect services.
Group of answer choices
True
False
2. A construction company may reduce its home office overhead percentage costs against individual projectsby:
Group of answer choices
B. Decreasing project overhead
B and D
A. Increasing company work volume
D. Downsizing the workforce
C. Getting involved with highly competitive work
3. ..........is a term synonymous with field overhead costs.
Group of answer choices
D. Material Costs
A or B
A. General Conditions
B. Indirect Costs
C. Direct Costs
4. In a Guaranteed Maximum Price (GMP) contract, the owner always covers costs above the GMP.
Group of answer choices
True
False
5. Which of the below reports is submitted by the trade contractor to the owner and is used as a guide for invoicing?
Group of answer choices
Construction Contract
Bid Form
Bar Chart Schedule
All of the above
Schedule of Values
6. Time card information recorded in the field is essential actual data for the accomplishment of which of the following task(s)?
Group of answer choices
Payroll
All of the above
Completion of invoices and/or requisitions
Job costing
Measurement of job site productivity
7.As facilities become larger in area, or greater in capacity, the construction cost increases, but not in linear proportion.
Group of answer choices
True
False
8. Which of these reasons would explain a negative schedule variance?
Group of answer choices
Added work requirements
Poor field supervision
All of the above
An unrealistic schedule baseline
Poor field productivity
9. When a construction company finds out that it's the low bidder on a new project, the good news is that they are the low bidder, and the bad news is that:
Group of answer choices
You are the low bidder and you cannot wait to get started
You are the low bidder and you may have "left some money on the table"
There are always unknowns in any project
The project might be extremely difficult
a and b
10. The overall responsibility for developing and monitoring a proper cost control system cannot be delegated entirely to the field?
Group of answer choices
True
False
11. What can the Contractor request from the Owner to help improve cash flow if an activity is 50% complete in a cost loaded CPM, but paid by the Owner only when activity is 100% complete?
Group of answer choices
A cash advance
Splitting the activity into two parts
A cost increase
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started