Question
1.Which of the following FAR citations outlines early exchanges with industry? FAR 15.201 FAR 12.501 FAR 14.201 FAR 25.101 2.What are pre-bid conference, pre-solicitation notices,
1.Which of the following FAR citations outlines early exchanges with industry?
FAR 15.201
FAR 12.501
FAR 14.201
FAR 25.101
2.What are pre-bid conference, pre-solicitation notices, and site visits all considered?
Mandatory for all procurements greater than $1M
Time-consuming and of little value
Unnecessary for complex requirements
Exchanges with industry
3.In general, who is the only person who may answer a prospective offeror's inquiry about a specific acquisition?
Program manager of the project
Contracting officer with contractual authority
Author of the requirement being acquired
Contracting specialist
4.Fill in the blank from the following alternatives: "After issuance of the solicitation, the evaluation factors for award and their relative importance cannot be changed without _______."
approval from the program manager
approval from potential offerors
first, canceling the solicitation and resoliciting the requirement
a formal amendment to the solicitation
5.You have provided one potential offeror with additional information necessary to prepare their offer. What must you do next with this information?
Make it available only to the firms you think will submit an offer
Make it available to the public as soon as practicable
Cancel the solicitation and then release a new solicitation to prevent unfair competitive advantage
Cancel the solicitation because there is an unfair competitive advantage
6.You issued a solicitation for 100 high-end, commercial off-the-shelf computers estimated at $230,000. Later that day, the customer informs you the quantity of computers needed has increased from 100 to 110. What should you do?
Proceed with receipt of offers, then issue a new solicitation for the additional computers
Mention the change in a pre-bid conference.
Issue a modification to the solicitation
Issue an amendment to the solicitation
7.The customer informs you that there is a change in the PWS; but you just issued your Request for Proposal three days ago. After reviewing the proposed change to the PWS, you determine that it is significant but does not exceed what could have been reasonably anticipated. What is your best course of action?
Amend the solicitation using the Standard Form 33 and extend the proposal due date
Mention the change in a pre-bid conference
Issue a modification to the solicitation and consider an extension to the proposal due date
Issue an amendment to the solicitation and consider an extension to the proposal due date
8.To whom must you provide a copy of all questions and answers generated at a pre-proposal conference?
Only the offerors who did not attend
All potential offerors, upon request
All the government employees on the acquisition team
Only the offerors that make the competitive range
9.You are the Contracting officer and need to post an amended solicitation and the changes will result in a need to extend the due date for proposals. Within the amendment you include: your office information (including your office name and address); the date of the solicitation; solicitation number; the date of the amendment; amendment number. You also describe the change. Are you ready to post the amended solicitation?
Yes, you have provided enough information
Yes, you dont need to include the solicitation closing date since that was in the original solicitation
No, you only missed the need to include the number of pages
No, you need to include the number of pages, the identity of the Government POC and their phone number and the revision to the due date
10.You have released your RFP on the GPE; it is a five year aircraft maintenance contract for a fleet of 25 aircraft. Two weeks later the Program Manager tells you the requirement has changed; they now need only one years worth of maintenance and the size of the fleet has been reduced to 5 aircraft. What should you do with your solicitation?
Update the solicitation to account for the change in requirements and new terms and conditions and reduce the response time because the scope of the effort has been reduced.
Abandon the solicitation and issue a new one to account for the change in requirements and new terms and conditions.
Cancel the solicitation and issue a new one to account for the change in requirements and new terms and conditions.
Amend the solicitation to account for the change in requirements and new terms and conditions.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started