Question
1-Which statement does not describe Burn Up Chart? a.It combines completed work and total work into a single line. b.Tracks completed work and total work
1-Which statement does not describe Burn Up Chart?
a.It combines completed work and total work into a single line.
b.Tracks completed work and total work with two separate lines.
c.The total work line communicates important information.
d.It includes the total work line that describes whether the project not yet complete because work is slow to be done, or too much new work is being added.
2-What is most important for your agile team to continuously focus on?
a.Understanding their tasks
b.Measuring their performance
c.Defining their tasks
d.Getting the right answers
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started