Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1.You are responsible for analyzing and quantifying cost and schedule performance on an Agile life cycle development project. During planning for the first sprint, the

1.You are responsible for analyzing and quantifying cost and schedule performance on an Agile life cycle development project. During planning for the first sprint, the development team decided on a sprint duration of 15 days and estimated they could complete 30 story points during the sprint. The development teams consists of five people with an aggregate daily cost of $500. Assume this is the daily sprint cost.

Note: Story points represent about equal amounts of work and are a way of estimating the scope of a product backlog item based on size and complexity. A large and/or complex product backlog item is worth more story points than a smaller and/or less complex product backlog item.

At the end of 10 days, the development team has completed only 17 story points. What is the equivalent EVM Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV), and Cost Performance Index (CPI)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

7th Edition

978-0470477151, 978-0-470-5562, 470556242, 0-470-55624-2, 9780470556245, 978-0470507018

Students also viewed these Accounting questions