1.You have a network with a critical path A-B-C-D.The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as
1.You have a network with a critical path A-B-C-D.The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below.
Task a m b Te Var
A 6 8 12
B 3 4 6
C 3 9 12
D 5 5 7
a.What is the value of for the network?
b.What is the value of 2 for the network?
c.What is the probability that this network can be finished within 27 days?