Question

1 Approved Answer

1.You have a network with a critical path A-B-C-D.The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as

1.You have a network with a critical path A-B-C-D.The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below.

Task a m b Te Var

A 6 8 12

B 3 4 6

C 3 9 12

D 5 5 7

a.What is the value of for the network?

b.What is the value of 2 for the network?

c.What is the probability that this network can be finished within 27 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Express English Legal System

Authors: Emily Finch, Stefan Fafinski

8th Edition

1292295457, 978-1292295459

More Books

Students also viewed these Law questions